Photos: 

Some evaluation reports are public and can be downloaded from this website, while others are restricted to MSF users and can only be accessed via Tukul. This limitation is mainly due to the sensitive nature of the operational contexts and the resulting content. However, there are internal discussions about making all evaluation reports publicly searchable. If you are an MSF association member, reports are made available on various associate platforms such as www.insideOCB.com.

Country/Region

RIDER, CRASH and Epicentre have finalized a critical review of the operations of MSF France in Borno, Nigeria, from 2015 to 2016.

***English and French version available***

This publication was produced by RIDER, CRASH and Epicentre.
01/03/2019

After seven years of existence and shortly before its closure, Cell 2 and the Direction of Operations launched a lessons-learned exercise of the Cardiovascular Emergency Project set at Hospital No. 9 in Grozny, Chechnya. The objective of this review was to relate the main steps and lessons of this so-called "atypical" medical project, at least in the light of MSF's experience, mobilizing a high-tech clinical expertise such as thrombolysis and angiography.

***English and French version available***

This publication was produced by MSF OCP, Cell2, in cooperation with RIDER.
01/03/2019

OCB has undertaken to learn from its emergency intervention to support the victims of Hurricane Matthew, during which it experienced difficulties providing shelter and reconstruction relief. The aim is to evaluate the distribution of reconstruction materials in remote and hard to reach areas covering the entire duration and geographical area; Grand’Anse and Sud Department from 6 October 2016 to 20 February 2017.

This publication was produced at the request of MSF OCB, under the management of the Stockholm Evaluation Unit. It was prepared independently by Malik Allaouna and Simon Deprez.
19/09/2017

OCBA commenced a new mental health intervention in the city of Buenaventura in February 2015 with the aim to support victims of violence. The project was set up to demonstrate an innovative approach with two principle elements: a) a focus on a mass media campaign as the main means of communication, and b) a provision of therapeutic sessions on the phone.

This publication was produced at the request of MSF OCBA, under the management of the Vienna Evaluation Unit. It was prepared independently by Helena Manrique.
30/08/2017

In 2015 MSF-OCB launched a review to assess the perception, by the field teams, of an increased organisational “bureaucratic” burden. The review spanned three phases, from problem identification, to an in depth field study, to a final phase of webinars to improve the coverage and overall accuracy of the findings. The review process culminated in 2 missions agreeing to pilot a new monitoring and reporting system based on the principles coming out of the review, starting asap.

This publication was produced at the request of MSF OCB, under the management of the Stockholm Evaluation Unit. It was prepared independently by Hélène Juillard, Marion Péchayre, and Lauren Weiss.
29/06/2017

In May 2016, concerns were raised at OCB HQ about the potential underestimation of the general IRFFG implementation costs. The OCB mission in Haiti had to retroactively disburse an unbudgeted 1.33M€ of severance pay to their staff, more than a year after the IRFFG implementation in the country.

This publication was produced at the request of OCB, under the management of the Stockholm Evaluation Unit. It was prepared independently by Yves Sonnay.
22/06/2017

Suite au séisme du 12 janvier 2010 en Haïti, MSF-OCG intervient en urgence dans la zone touchée et offre des soins aux blessés. Alors qu’une grande partie des structures de santé de la zone affectée par le séisme sont endommagées ou détruites, MSF-OCG décide de s’impliquer rapidement dans une intervention à moyen terme, soit la mise en place d’un hôpital en container de 120 lits sur la commune de Léogâne (épicentre du tremblement de terre où 80% des bâtiments ont été détruit).

This publication was produced at the request of MSF OCG, under the management of the Vienna Evaluation Unit. It was prepared independently by Federica Alberti, Annie Desilets and Yves Sonnay.
21/09/2016

In 2010 the operational prospects for OCB (strategic operational plan) outlined the broad objectives for the coming three years and placed renewed attention on key medical areas including surgery and emergency and acute medicine, bringing about increased investment in two hospital programs where OCB focussed on providing emergency surgical care in third level facilities in Tabarre and Kunduz.

This publication was produced at the request of MSF OCB, under the management of the SEU. It was prepared independently by Juan Luis Dominguez and Jon Gunnarsson.
29/10/2015

The evaluation looks at the process for managing MSF-OCP's construction/rehabilitation projects since 2012. The main problems identified are not related to the process itself, but the way it is put into application. The main users pointed out the long delays (periods of indicision) as being the biggest difficulty, followed by budget/cost issues (cost/m² estimates) , and the quality of constructions (techniques, materials, etc). One of the root causes of delays relates to unclear/incomplete definition of roles and responsibilities = actions to take.

Nicolas Bérubé & Vincent Brown
16/07/2015

The purpose of this evaluation was to assess the functioning of the hospital set-up in Léogâne, Haiti one year after its implementation and to capture the lessons learned in order to inform other missions that attempt this type of set-up. The conclusions are based on two visits, the first at the 6-month mark and the second approximately one year following the initial implementation. In general, there is a positive attitude towards the set-up and the advantage of quick and relevant decision-making was felt in most departments at almost all levels.

This evaluation was conducted by Annie Désilets on behalf of the MSF Vienna Evaluation Unit.
01/06/2015

Pages